County GovernmentTop story
Pottawattamie County approves $390,000 to design jail HVAC upgrades
$390,000approved for Phase I design and bidding help on the jail HVAC project
Supervisors voted unanimously Tuesday.
Sources: KMAland.com, Daily Nonpareil
Pottawattamie County supervisors unanimously approved $390,000 Tuesday for design services and bidding help on the first phase of heating, ventilation and air conditioning improvements at the county jail, KMAland.com reported. The Daily Nonpareil also reported the $390,000 approval for the first phase of engineering work. The jail was built in 1998.
Buildings and Grounds Director Jason Slack said nothing is failing right now. Sheriff Andy Brown did replace a bad air handler motor last week. Slack called it "aging infrastructure that is due to be replaced."
- Design team: IMEG, ETI and Emergent Architecture
- Work timing: spring and summer, one air handler at a time
- Still to come: more engineering fees for construction and commissioning
The jail project is planned in phases over years
- 6 months
- expected for design and bidding help
- 3 years
- Slack's realistic estimate for the project
- 1998
- year the jail was built
Source: KMAland.com